The Boardman to Hemingway Transmission Line is an approved, not yet constructed, facility that includes an ASC approved route approximately 270.8-mile-long single-circuit 500-kV electric transmission line that crosses five counties in Oregon, Morrow, Umatilla, Union, Baker, and Malheur counties. The approved facility also includes four ASC alternative routes of approximately 33.3 miles of transmission line. The RFA1 approved routes include four alternative 500-kV transmission line routes equaling approximately 8.8 miles. The approved facility also includes roads, communication stations, the Longhorn Station, and temporary construction areas. | Under review/Approved. On September 27, 2022, Council approved the Final Order on ASC and issued a site certificate for the facility. On September 22, 2023, Council approved the Final Order on RFA1 and issued the first amended site certificate. The approved but not yet constructed facility has a construction commencement deadline of October 6, 2026.
On April 11, 2024, the Department received a complete Request for Amendment 2 (RFA2) to the Boardman to Hemingway Transmission Line Site Certificate from the certificate holder. RFA2 seeks Council approval to: - Add micrositing areas to allow siting of previously approved facility components in new locations. The proposed micrositing area additions include approximately 40 miles of 500-kV transmission line alternatives in each of the five affected counties, with 98.5 miles of associated access road modifications, and 0.6 mile of 230-kV transmission line alternatives; refining 58 miles of roads resulting from additional design and engineering, and the addition of temporary construction work area alternatives.
- Expand the site boundary for portions of the facility, and separate the definition of micrositing areas and the site boundary. The micrositing areas are more narrow areas that are evaluated and, if approved, would be where facility components could be located.
- Amend specific site certificate conditions.
- Add a Midline Capacitor Station within the previously approved site boundary/micrositing area, and adjacent to an existing substation in Union County.
- Redefine the widths for temporary roads.
Public Comment Period: A 45-day comment period is now open. Comments will beare accepted beginning April 16 through May 30, 2024, until the close of the public hearing listed below, unless extended by Council. The public may comment on RFA2, DPO, and DPO Attachments including the amended site certificate and revised conditions, which are available below.
Public Hearing: Date: Thursday, May 30, 2024 Start Time: 5:30 p.m. Pacific End Time: no earlier than 6:30 p.m. Location: Port of Morrow Riverfront Center/Riverfront Room 2 Marine Dr NE, Boardman, OR 97818 Webinar Link: https://odoe.webex.com/odoe/j.php?MTID=mb8602b18617f34376e0f8603b862a8db Webinar Event Number: 2330 219 1379 Webinar Event Password: EFSC (3372 from phones and video systems) Teleconference: 408-418-9388 Teleconference Access code: 2330 219 1379 Written comments to be included on the record of the DPO public hearing must be received by the comment deadline, submitted at one of the hearings, through ODOE's online comment portal, or by mail, email, or fax to: Kellen Tardaewether, Senior Siting Analyst Oregon Department of Energy 550 Capitol Street NE, 1st Floor Salem, OR 97301 Email: kellen.tardaewether@energy.oregon.gov Fax: 503-373-7806
| Morrow, Umatilla, Union, Baker, Malheur, Owyhee (Idaho) counties.
| Applicant/Certificate holder:
Idaho Power Company | ODOE contact:
Kellen Tardaewether | Applicant/Certificate holder contact:
Joe Stippel | |
|